Interpool Spa

Sukhumvit Hospital, Bangkok

This project involved the installation of a hydrotherapy system at Sukhumvit Hospital, where Interpool Spa developed a prefabricated fiberglass pool designed to support hydrotherapy and structured physical recovery within a medical environment. The hospital is located on Sukhumvit Road near BTS Ekkamai, placing the project within a dense urban building context with clear site constraints.

One of the main challenges was lifting the prefabricated pool to the 9th floor, approximately 40 meters above ground, using a crane. The installation had to be carried out within a restricted working area and required a 55-person team to complete the process with precision and safety.

Coordination of a 55-person team, and execution within a live medical facility where safety and precision were non-negotiable at every step.

The Challenge

Installing a prefabricated fiberglass pool on the 9th floor of a functioning hospital — approximately 40 meters above a dense urban street — required a crane operation in severely restricted conditions, coordination of a 55-person team, and execution within a live medical facility where safety and precision were non-negotiable at every step.

The Result

A fully operational hospital hydrotherapy pool delivered on the 9th floor without incident — one of Interpool Spa’s most logistically complex installations, and a clear proof point that the company can execute technical, high-stakes projects in conditions that most contractors would not attempt.

  • Date: May 5, 2026
  • Layout (Explain Layout)
  • Design Code: (Input Design Code)
  • Created By: Interpool Spa Design
  • Book now
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare